Request For Information
Please use the above form to request additional information or further analysis of any aspect of the current design or to inform us that additional information has come to light and requires further investigation.
During the course of the build, all requests for information must be made via an ‘RFI Form’ and should be submitted to rfi@bewengineering.co.uk.
We operate a two business day reply guarantee that will only apply where the RFI form is completed and submitted and contains all the necessary information in order to answer the query. Where further information is deemed to be necessary, we will request this and the two days will start from the day that all the requested information is received.
Where an RFI form indicates that a site visit is necessary, we will aim to conduct this within one week and supply any additional information necessary within two business days of the visit.
Our two-business day reply guarantee excludes the dates between the 23rd December and the 3rd January. It also excludes four more weeks of the year that will be published below. You should check these dates at the start of the project and then periodically during the project as these dates can be updated and changed at any time.
Dates excluded from reply guarantee
- 24th August to 4th September
- 23rd December to 3rd January